August 21, 2024 1:14 PM
Paving Schedule Updated
Starr Road is closed between Penn Green and Newark Roads to through traffic for the wearing course. This is the final step in the paving process for Starr Road. Tomorrow, the paving contractor will be working on Starr between Penn Green and Ellicott Roads.
The tentative schedule (weather permitting) for the rest of the paving program will be as follows:
August 21st – Starting wearing course on Paving on Starr Road between Penn Green Road and Pelham Drive
August 22nd - Finish wearing course on Starr Road between Penn Green and Ellicott Roads
The work will generally take place between 6:30am and 6:30pm and each road section will be closed to through traffic. Residents and local deliveries will be able to access properties within the work zones but through traffic will need to seek alternate routes of travel.
Please obey all signage during the work. We will do our best to have flaggers at intersections to aid everyone in getting to where they need to go with minimal inconvenience.